A monthly client package
Compare all team hours with the same agreed allowance. Count delivery, reviews and management consistently so the available time is not overstated.
Features
When the work has an agreed hours limit, a total at month-end comes too late. Check progress as you go and decide how to use the time that remains.
Start for freeHours and minutes
Eight of the agreed 40 hours remain. Compare that with the work still to do. If the remaining tasks need more time, discuss the scope before the allowance runs out.
A project can look small until you add up everyone’s work. Extra meetings and revisions gradually use hours that were originally intended for the main tasks.
Set a weekly or monthly project time plan in EXPANS and compare it with recorded hours. An hours budget is separate from a financial estimate: it does not automatically account for all business costs and revenue.
When it helps
Compare all team hours with the same agreed allowance. Count delivery, reviews and management consistently so the available time is not overstated.
When requests arrive unevenly, a shorter period prompts earlier priority reviews. Decide which tasks fit into the remaining hours based on their importance.
The shared budget covers combined team hours, not just the manager’s time. Check that everyone has entered their work and pending entries have been confirmed before reviewing the balance.
EXPANS · Features
Use the agreed weekly or monthly hours. Check whether account management, internal reviews and communication are included.
Assign the responsible people to the project and ask them to check their budget notification preferences. Workspace permissions still determine access to the data.
As recorded hours approach the plan, review unfinished tasks. Defer lower-priority work, change the order or agree on additional hours.
Useful details
Decide which period the allowance covers and what work belongs in it. Forty hours a month might include delivery, revisions and meetings. The team needs to count them the same way.
| Detail | Example | Question to agree on |
|---|---|---|
| Period | 40 hours per month | Does the agreement cover this exact period? |
| Included work | Delivery, revisions and management | Does everyone count the same activities? |
| Recipients | Responsible project members | Are the relevant alerts enabled? |
| Next action | Review priorities as the limit approaches | Who can agree to additional scope? |
Let’s look at an example
The sample monthly plan allows 40 hours. The team has recorded 32: 24 on the main work, 5 on revisions and 3 on communication. That uses 80% of the budget and leaves 8 hours. It is a balance calculation, not a forecast of completion.
Suppose the unfinished agreed tasks need another 12 hours. That leaves a 4-hour gap. Before continuing, choose whether to reduce scope, defer tasks or agree on more time. Changing the budget number alone would hide the planning issue rather than resolve it.
Example
We’ve used 32 of the 40 hours, leaving 8. The unfinished tasks need about 12 more. Before continuing, let’s choose the priorities that fit into 8 hours or agree on another 4. We’ll first check that everyone has entered their time so we are making the decision from a complete record.
Common mistakes
If management is included in the agreement, include its hours in the comparison. Counting only production would make the balance look larger than it is.
Use the message to prompt a task review. It cannot choose what to defer or how many hours to add.
Assignments help determine who receives budget notifications. They do not hide the project from the rest of the team; workspace permissions control visibility.
Make a brief review routine: recorded hours, remaining allowance, unfinished tasks and a decision about them. Up-to-date entries make that review useful. Hours added only at month-end cannot help you adjust the plan earlier.
An overrun does not always mean someone made a mistake. New requirements or agreed urgent work may explain it. Keep task descriptions clear enough to distinguish an intentional scope change from an unnoticed workload problem.
First steps
FAQ
No. It helps you compare planned and recorded hours and review the work in time. The user stops the timer; discuss an overrun with the team and client.
A project budget covers time spent on a particular project. A personal work plan describes the hours a person aims to work over a period.
Recipients depend on project assignments, permissions and personal notification settings. Check these before the team starts.
Select the package’s dates in a report and compare recorded hours with the agreed allowance. Automatic project plans run weekly or monthly, so their periods may differ from the contract dates.
Not necessarily. Check the deliverables, expected scope and completeness of the time records. Hours remaining do not measure the quality of the work.
Check the entries and the reasons for extra work, then agree on the next plan. Keep genuine work in the record rather than deleting hours to make the total fit.